Hope you had a good break and all ready for 2021!
I would like to give you an update on the Richmond unit as it is experiencing intermittent data gaps issue (including
some hours) since deployment on the 18 Dec 2020.
The unit (2250 plus microphone) was fully replaced on the 23 Dec but still seeing data gaps. It is currently not
contactable so we have arranged contractor to re‐visit tomorrow morning.
We will keep you posted with outcome. Robert will also contact you in regards to the location of this unit – it is
not picking up 30‐50% of RNP arrival RWY 12 operations as these turning operations are about 1.7KM away from the
monitor, often they not generating enough noise above the day threshold of 55dB to create a valid event.
Below is a table of daily hourly count since deployment.
Daily
Date
Hourly
Comments
18‐Dec‐20
18
19‐Dec‐20
21
20‐Dec‐20
23
*Hardware replaced including microphone on 23 Dec 2020. CMS356697
21‐Dec‐20
21
22‐Dec‐20
23
23‐Dec‐20
19
24‐Dec‐20
11
25‐Dec‐20
14
26‐Dec‐20
0
27‐Dec‐20
8
28‐Dec‐20
24
*Replacement unit also unstable with data gaps (CMS35998)
29‐Dec‐20
20
Waiting for Contractor to visit on 5 Jan 2021 morning
30‐Dec‐20
0
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
31‐Dec‐20
0
01‐Jan‐21
0
02‐Jan‐21
0
03‐Jan‐21
0
Released
Kind Regards
s47F
1

Doc 18
FoI 24-52
From: s47F
Sent: Tuesday, 22 December 2020 4:33 PM
To: s47F
@envirosuite.com>;s47F
@envirosuite.com>; s47F
s47F
@envirosuite.com>; s47F
@envirosuite.com>
s47F
Cc:
@envirosuite.com>; s47F
@envirosuite.com>; s47F
s47F
@envirosuite.com>;s47F
@envirosuite.com>
Subject: ASA/HBA ‐ CMS358422, NMT375 Richmond unit not stable
Hi s47F
Thank you for looking at NMT375 today. As per our discussion, while waiting for Denmark’s response, please go
ahead to organise for contractor to visit site to replace the unit at the earliest time. We can always cancel the visit if
there is useful information from Denmark.
Following is an image showing all the one sec data gaps from this unit since deployment from 18 Dec. The grey
areas are gaps where no events are recorded and hence won’t match to aircraft. In many cases, WebTrak is still
showing noise level for this grey gap period due to data to WebTrak is live stream of the noise level not events. This
means there will be confusion for the end users (public), it they map report a noise complaint by looking at the
WebTrak data but ANOMS won’t have events correlated to the aircraft.
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Thank you for your help.
s47F
Released
From: s47F
Sent: Monday, 21 December 2020 4:53 PM
To: s47F
@envirosuite.com>; s47F
@envirosuite.com>; s47F
s47F
@envirosuite.com>; s47F
@envirosuite.com>
Cc: s47F
@envirosuite.com>; s47F
@envirosuite.com>; s47F
2
Doc 18
FoI 24-52
s47F
Subject: ASA/HBA ‐ CMS358422, NMT375 Richmond unit not stable
FYI the ticket no is CMS358422. There are many short hourly records too, maybe unit keep restarting?
Ticket now with NMT team.
EMSOC – Reminder that HBA now has 3 monitors, daily check is to have ticket for any data issue.
Thanks
s47F
From: s47F
Sent: Monday, 21 December 2020 4:40 PM
To: s47F
envirosuite.com>; s47F
envirosuite.com>; s47F
s47F
@envirosuite.com>; s47F
@envirosuite.com>
Cc: s47F
@envirosuite.com>
Subject: ASA/HBA ‐ NMT375 Richmond unit not stable
Hi s47F
NMT375 Richmond unit not stable. It is missing some hours every day. I will create a ticket very soon.
Can you check and see if site visit is required?
Hourly
Date
RMTID
Count
18‐Dec‐20
375
18
19‐Dec‐20
375
21
20‐Dec‐20
375
23
21‐Dec‐20
375
14
Thanks
s47F
From: s47F
@envirosuite.com>
Sent: Monday, 21 December 2020 3:58 PM
To: s47F
@envirosuite.com>; s47F
@envirosuite.com>
Cc: s47F
@envirosuite.com>
Subject: RE: Hobart NMT Deployment update & status
Hi s47F.
We need to submit by COB tomorrow – so preferably before then.
Just for next time, if we can’t get it done by planned date (Which was 18/12) then please provide heads up.
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Thanks
s47F
From: s47F
Released
@envirosuite.com>
Sent: Monday, 21 December 2020 3:06 PM
To: s47F
@envirosuite.com>; s47F
@envirosuite.com>
Cc: s47F
@envirosuite.com>
Subject: RE: Hobart NMT Deployment update & status
3

Doc 18
FoI 24-52
Hi s47F,
s47F will have them complete and submit by COB tomorrow.
s47F
To help protect you r priv acy, Microsoft Office prevented automatic download of this picture from the Internet.
Manufacturing Manager
s47F
s47F
| W: www.envirosuite.com / www.emsbk.com
Formerly EMS Brüel & Kjær
A: Level 12 432 St Kilda Road Melbourne VIC 3004 AU
From: s47F
@envirosuite.com>
Sent: Monday, 21 December 2020 2:58 PM
To: s47F
@envirosuite.com>; s47F
@envirosuite.com>
Cc: s47F
@envirosuite.com>
Subject: FW: Hobart NMT Deployment update & status
Importance: High
Hi s47F
.
As per schedule below, have you completed and Site Suitability and Commissioning Checklists for the HBA x3 NMT
and WS? (was supposed to be completed FRI)
Can you please share, as this information and documents need to be submitted to Airservices as part of our report
that we send out tomorrow COB.
Thanks
s47F
From: s47F
Sent: Wednesday, 16 December 2020 6:35 PM
To: s47F
envirosuite.com>; s47F
@envirosuite.com>; s47F
s47F
@envirosuite.com>; s47F
envirosuite.com>; s47F
s47F
@envirosuite.com>;s47F
@envirosuite.com>; s47F
s47F
Cc: s47F
@envirosuite.com>; s47F
@envirosuite.com>; s47F
s47F
@envirosuite.com>; s47F
@envirosuite.com>
Subject: Hobart NMT Deployment update & status
Importance: High
Hi All.
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
s47F
, well done with deploying the monitors.
s47F
, thanks for working through the data streaming issues today.
The table below is updated with the progress of tasks for the HBA STM deployments (x3).
Released
In summary all x3 NMTs have been deployed along with the x1 Weather Station – we are just awaiting data
confirmation in ANOMS which is expected to be verified tomorrow morning.
Key milestones for the remaining tasks:
s47F
‐ Confirm Noise events and weather data streaming into ANOMS ‐
THU 17/12
4
Doc 18
FoI 24-52
Lawrence ‐ enable the monitors on WT ‐
FRI 18/12 Noise Office ‐ Complete final threshold setup and submit deployment reports
WED 23/12
As I will be travelling tomorrow(PM) and Friday, please let me know if there are any issues with or while completing
your allocated tasks, to ensure that the monitors are collecting data and on WT on
FRI 18/12 Rgds
s47F
From: s47F
Sent: Friday, 11 December 2020 10:49 AM
s47F
To:
@envirosuite.com>; s47F
@envirosuite.com>; s47F
s47F
@envirosuite.com>; s47F
@envirosuite.com>
s47F
Cc:
@envirosuite.com>; s47F
envirosuite.com>; s47F
s47F
@envirosuite.com>;s47F
@envirosuite.com>; s47F
s47F
@envirosuite.com>
Subject: FW: Hobart Deployment Briefs [SEC=OFFICIAL]
Importance: High
Hi s47F
Please see the Planning schedule for Airservices STM deployment in HBA.
As we reviewed today I would suggest being onsite the latest
Tue 15/12 and we need to have these deployed and
operational by
Fri 18/12.
Before going ring and organise to meet the residents so you know they will be home.
s47F
will sign off the contractor for this work, so we are all ready to go next week.
This deployment is very sensitive and important to Airservices, s22
If there are any escalation or prioritisation required please let me know, both myself ands47F are here to support
you to ensure this gets done.
Rgds
s47F
Schedule Planning:
We are working towards having this installed and operational in ANOMS:
Start Date: FRI ‐18 Dec
REF
WHAT
WHO
WHEN
1
Deployment Briefs received from ASA
ASA ‐ s47F
Completed
2
ASA to provide possible deployment locations (options for 2 of
ASA ‐ s47F
Completed
3 deployments provided)
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
3
Confirm sign off contractor for HBA (recomm) & prepare
s47F
Completed
training material
4
Inform ASA of new contractor selected for HBA works
s47F
Completed
Released
3
Prepare and test the x3 STM monitors in house
s47F
Completed
‐
NATA certified
‐
Test inhouse that NMTs are working and synch to
Not tested
FOCUS
through to
‐
Test x1 Weather Station is working
ANOMS in office
5
Doc 18
FoI 24-52
4
Send x3 STM and x1 WS to site (to contractor) – to be in HBA
s47F
Completed
Monday
5
Review “offers” spreadsheet from Airservices & Organise to
s47F
Completed
meet residents
‐
Verify on map most suitable locations with reference
to Flight path
‐
Verify from maps ISO compliant options (No large trees
or likely other noise sources)
‐
Call residents to organise a meeting time trip next TUE
6
Fly to site and:
s47F
Completed
‐
Negotiate final locations in each zone (ensure ISO
compliant + clear line of site to Aircraft)
‐
Complete
Site Suitability checklist
‐
Organise agreement with owners (offering $300 for 6
months + repair works once complete)
‐
Install monitors – complete
Commissioning checklist +
photos
‐
Setup the monitor in focus + ensure operational
‐
Once complete notify Rob Drozdz and May Wu (Noise
Office)
7
Setup monitor in ANOMS + weather station
Noise Office/ OC –
Completed
‐
Ensure Lat/Longs are correct
MW& KC
‐
Ensure noise data is streaming into ANOMS
TSG – John L
For weather stations:
‐
Correlate weather with NMT data at Connolly’s Marsh
‐
Tag NE that have windspeed > 10m/s
‐
Ensure noise and weather data are linked in the system
8
Make monitors live on WT
TSG – LM &
Completed
Noise Office KC
9
Complete documentation and upload to FOCUS for Noise office Keith Tan / Bo
FRI 18/12
team
Feng
‐
Site Suitability checklist
‐
Commissioning checklist + photos
10
Threshold ‐ review and set
Noise Office
By Tue 22/12
11
Deployment Report
Noise Office
Wed 23/12
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
The excel spreadsheet (attached( has the details of residence who have agreed to have the monitor installed at their
location. The KMZ file maps (Attached) provide the address of each location
“offer”)
Primrose Sands ‐ There are a number of residents in the following locations that we can approach – note I
know
Released the area, I can propose which areas would be best to avoid wind
Connollys Marsh – the 1 resident in the zone has agreed to have the monitor installed at a building that has
power (weather station required)
Richmond – Belinda mentioned a resident outside the zone and that we need to try and organise within a
resident within the zone, and default to this person as last resort
6

Doc 18
FoI 24-52
Connolly’s Marsh (includes weather station)
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released
Primrose Sands
7

Doc 18
FoI 24-52
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released
Richmond
8

Doc 18
FoI 24-52
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released
9
Doc 18
FoI 24-52
From: s47F
@AirservicesAustralia.com>
Sent: Thursday, 10 December 2020 11:16 AM
To: s47F
@envirosuite.com>
Cc: s47F
@envirosuite.com>; Community Engagement Airservices
<xxxxxxxxxxxxxxxxxxx@xxxxxxxxxxxxxxxxxxxx.xxx>; s47F
@AirservicesAustralia.com>;
s47F
@AirservicesAustralia.com>
Subject: [WARNING: UNSCANNABLE EXTRACTION FAILED]RE: Hobart Deployment Briefs [SEC=OFFICIAL]
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize
the sender and know the content is safe.
Hi s47F
Looking forward to speaking with you in about an hour re Hobart. Offers to host the STMs in Hobart closed last night
so I can now provide a list of offers which may be suitable. Attached is both a KML and spreadsheet, with contact
details for those who have offered their property.
Connellys Marsh – property under flightpath has made offer. Only suitable offer in area.
o If problems identified with site and installation can’t progress (not anticipated but just in case) –
please just focus on the properties in Connellys Marsh nearest to the flightpath.
Richmond zone – As mentioned earlier in the week, the offers received in this area aren’t preferred. Please
approach landowners in the zone initially.
o One offer from the area has been provided in the attached but should only be used as a back‐up
option, if homes in the zone refuse or residents aren’t at home to be approached.
Primrose Sands zone – There are 22 offers that may be suitable in this area. There are clear area groupings,
so I have provided all potentially suitable offers so they can be considered on the ground (and based on
resident availability).
Speak with you soon.
Kind regards
s47F
s47F
Senior Environment and Noise Specialist
Airservices Australia
s47F
@airservicesaustralia.com
CAUTION: This e-mail is confidential. If you are not the intended recipient, you must not disclose or use the
information contained in it. If you have received this e-mail in error, please tell us immediately by return e-mail and
delete the document.
Airservices Australia does not represent, warrant or guarantee that the integrity of this communication is free of errors,
virus or interference.
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
From: s47F
Sent: Tuesday, 8 December 2020 2:08 PM
To: s47F
@envirosuite.com>
Cc: s47F
@envirosuite.com>; Community Engagement Airservices
s47F
Released
@AirservicesAustralia.com>; s47F
@AirservicesAustralia.com>
Subject: RE: Hobart Deployment Briefs [SEC=OFFICIAL]
Hi s47F
Just an update on the progress of offers from the community, for sites in the Hobart area.
10
Doc 18
FoI 24-52
For Connellys Marsh, the only property in the zone has offered their property to host the NMT which is good
so I’ll ask you to install at that location.
For Primrose Sands area, there are a range of offers which look good across the zone so sourcing a site from
those options will definitely be achievable.
For the Richmond Zone, the offers so far are outside the preferred zone. Based on offers so far, landowners
in the zone will need to be approached in the first instance. If your team haven’t already looked at the
options for this zone, if you can get them to have a look please.
o I will provide the few offers that we have received which may be a back‐up, if a site in the zone can’t
be sourced.
Nomination as a potential site is open until COB Thursday, so I’ll provide a list of potentially suitable sites as soon as
possible on Friday.
For site inspections and installations, is the plan for everything to be completed next Monday (14th) or will it be
across a few days? Bridget is looking to provide an update to any landowners who’s home we have identified as
potential sites, so it would be good to understand the likely timing they can expect.
NB – All landowners have been advised that if EVS determine their property is an appropriate host, an agreement
etc will be setup by your team with them.
Let me know if you have any questions at this stage.
Kind regards
Belinda
s47F
Senior Environment and Noise Specialist
Airservices Australia
e s47F
@airservicesaustralia.com
CAUTION: This e-mail is confidential. If you are not the intended recipient, you must not disclose or use the
information contained in it. If you have received this e-mail in error, please tell us immediately by return e-mail and
delete the document.
Airservices Australia does not represent, warrant or guarantee that the integrity of this communication is free of errors,
virus or interference.
From: s47F
@envirosuite.com>
Sent: Wednesday, 25 November 2020 8:55 AM
To: s47F
@AirservicesAustralia.com>
Cc: s47F
@envirosuite.com>; s47F
@AirservicesAustralia.com>;s47F
s47F
@AirservicesAustralia.com>; Community Engagement Airservices
<xxxxxxxxxxxxxxxxxxx@xxxxxxxxxxxxxxxxxxxx.xxx>
Subject: RE: Hobart Deployment Briefs [SEC=OFFICIAL]
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Great s47F – thanks for the confirmation.
s47F
Released
From: s47F
@AirservicesAustralia.com>
Sent: Wednesday, 25 November 2020 8:18 AM
s47F
To:
@envirosuite.com>
Cc: s47F
@envirosuite.com>; s47F
@AirservicesAustralia.com>; s47F
s47F
@AirservicesAustralia.com>; Community Engagement Airservices
11
Doc 18
FoI 24-52
<xxxxxxxxxxxxxxxxxxx@xxxxxxxxxxxxxxxxxxxx.xxx>
Subject: RE: Hobart Deployment Briefs [SEC=OFFICIAL]
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize
the sender and know the content is safe.
Hi s47F
Just to confirm, we will provide confirmation of any “host” sites for the noise monitors by COB on the 10th. I’ll aim
for us to provide a few updates between now and then however.
In terms of timing impacts, this will result in the modified timings we discussed earlier this week, of:
Deployment start of the week of Monday 14th December
Aiming for noise monitors to be on WebTrak, 18th December
Kind regards
s47F
s47F
Senior Environment and Noise Specialist
Airservices Australia
es47F
@airservicesaustralia.com
CAUTION: This e-mail is confidential. If you are not the intended recipient, you must not disclose or use the
information contained in it. If you have received this e-mail in error, please tell us immediately by return e-mail and
delete the document.
Airservices Australia does not represent, warrant or guarantee that the integrity of this communication is free of errors,
virus or interference.
From: s47F
@envirosuite.com>
Sent: Monday, 23 November 2020 10:26 AM
To: s47F
AirservicesAustralia.com>
Cc: s47F
@envirosuite.com>; s47F
AirservicesAustralia.com>; s47F
s47F
@AirservicesAustralia.com>
Subject: RE: Hobart Deployment Briefs [SEC=OFFICIAL]
No Problem s47F .
So does this mean we should expect to know if Airservices have a location sorted by say
THU 10th Dec
Rgds s47F
.
From: s47F
@AirservicesAustralia.com>
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Sent: Friday, 20 November 2020 5:23 PM
To: s47F
@envirosuite.com>
Cc: s47F
@envirosuite.com>;s47F
@AirservicesAustralia.com>; s47F
s47F
AirservicesAustralia.com>
Subject: RE
Released : Hobart Deployment Briefs [SEC=OFFICIAL]
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize
the sender and know the content is safe.
Hi s47F
12
Doc 18
FoI 24-52
Apologies, there’s some concerns about receiving community site offers by 7 December. Would it be possible to
push back the noise monitor installations to the week of 14 December?
Kind regards
s47F
s47F
Senior Environment and Noise Specialist
Airservices Australia
e s47F
@airservicesaustralia.com
CAUTION: This e-mail is confidential. If you are not the intended recipient, you must not disclose or use the
information contained in it. If you have received this e-mail in error, please tell us immediately by return e-mail and
delete the document.
Airservices Australia does not represent, warrant or guarantee that the integrity of this communication is free of errors,
virus or interference.
From: s47F
@envirosuite.com>
Sent: Tuesday, 17 November 2020 5:44 PM
To: s47F
@AirservicesAustralia.com>
Cc: s47F
@envirosuite.com>; s47F
@AirservicesAustralia.com>
Subject: RE: Hobart Deployment Briefs [SEC=OFFICIAL]
Great thanks s47F
I’ll give you a call if I have any questions.
Rgds
R.
From: s47F
@AirservicesAustralia.com>
Sent: Tuesday, 17 November 2020 4:26 PM
To: s47F
@envirosuite.com>
Cc: s47F
@envirosuite.com>; s47F
@AirservicesAustralia.com>
Subject: [WARNING: UNSCANNABLE EXTRACTION FAILED]Hobart Deployment Briefs [SEC=OFFICIAL]
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize
the sender and know the content is safe.
Good afternoon s47F
Thanks for your time earlier. As discussed, please find attached three deployment briefs for:
Connelly’s Marsh
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Primrose Sands
Richmond
in Hobart. A KML including the three zones is attached.
Released
Key points:
Objective:
To support PIR of changes made in November 2019.
Timing:
Airservices approaching community to request “hosts” for the noise monitors. Any suitable offers we
receive will be provided to EVS on 4 December.
13

Doc 18
FoI 24-52
EVS on‐ground site identification and installation – week of 7 December
Noise monitors to be online from 14 December
Notes around deployments:
Primrose Sands – to avoid wind/wave impacts, its hoped a site away from the shore can be obtained.
Connelly’s Marsh is anticipated to be affected by wind. Basic weather station to capture wind (to identify
affected events) required.
o Only one collection of buildings in this zone. We are hoping landowners offers to host NMT,
otherwise targeting as close to the zone as achievable.
Let me know if you have any initial questions. I’m sure we’ll have a few chats about this over the next few weeks
though.
Kind regards and thanks
Belinda
s47F
SENIOR ENVIRONMENT AND NOISE SPECIALIST
s47F
@airservicesaustralia.com
Alan Woods Building
25 Constitution Avenue, Canberra ACT 2600
CAUTION: This e-mail is confidential. If you are not the intended recipient, you must not disclose or use the
information contained in it. If you have received this e-mail in error, please tell us immediately by return e-mail and
delete the document.
Airservices Australia does not represent, warrant or guarantee that the integrity of this communication is free of errors,
virus or interference.
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released
14