Evidence based guidelines for diagnosis, management and treatement of ADHD
Registration date
14‐August‐2019
NHMRC advise developer of whether CEO agrees to consider
NHMRC response within 2‐4 weeks
Signed 6 Sept, GD letter sent 13 Sept 2019
Estimated Commencement date
01‐July‐2019
Systematic Review end date
Submission of progress report before PC
6 months prior and no later than 3 months prior
NHMRC feedback to progress report
Feedback within 4‐8 weeks of report receipt
SR to PC
Arrange Methodological Review
< or =
12 months
SR to
Confirm PC dates with NHMRC
Submission
2 weeks prior to start of PC
< or =
20 months
Provide all PC docs to NHMRC
5 days prior to start of PC
Public Consultation
01‐February‐2021
Last advice 23 Jan 2020
Notify NHMRC of intended date to submission
PC to
2 months prior to submission date
Submission
< or =
8 months Date for Submission to NHMRC
Submission to NHMRC must be
Mid April 2021
2 months prior to Council
Council usually meets three times a year (Mar, June, October)
16‐17 June 2021
Last advice 23 Jan 2020
NHMRC notify Guideline Developer of Council Outcome
4 weeks from Council date
Publish & Disseminate Guideline
16 weeks post approval