This is an HTML version of an attachment to the Freedom of Information request 'ARPANSA business case'.



 
 
Business Case 
ARPANSA-PM-TMP-002 
General details 
General 
Project number (if known): 
PRO-0025 
Idea/Project name: 
Waste Storage Area 
Proposer/Project Manager: 
Marcus Grzechnik 
Project Owner: 
Gillian Hirth 
Section: 
MERS/RHS 
Start date: 
Already initiated 
End date: 
December 2018 
Duration: 
 
Executive summary 
Summary of business case 
Between the late 1920’s to the 1970’s, the Commonwealth Radiation Laboratory (CRL) existed on a site 
at University of Melbourne (UoM). The activities that were conducted at the CRL during this time 
resulted in legacy contamination. Because of this the Commonwealth (represented by ARPANSA) is 
accepting responsibility for the waste produced from remediation of the site. Approximately 210 drums 
containing soil and building material contaminated with radium-226 require storage in a licenced 
radioactive waste storage facility. 
While the activities were carried out by a predecessor to ARPANSA, it is considered good practice that 
ARPANSA take care of the legacy. ARPANSA expects other organisations to take care of their legacy 
waste, as such  we should lead by example. 
The drums of legacy low-level radioactive waste are to be transferred to the Yallambie site from 
Melbourne University.  Several options have been considered in a SWOT analysis (attached), where the 
construction of an area to store the waste within the ARPANSA building is the preferred option. 
 
Recommendations – what would you like the EG to approve? 
The EG previously approved; 
-  The proposed direction, including where the legacy waste should be located (within 
ARPANSA’s facility) 
-  The transportation costs for the  initial tranche of 72 drums (approximately $5K) 
-  Commissioning of the design for the proposed storage areas 47G - business
 
Business Case v1.0 
ARPANSA-PM-TMP-002 
 
1 of 5 


The EG will be asked to approve the budget for the building cost following design completion and receipt 
of the tender bids.  Based on the design, we expect the costs to be circa $250K. 
Background 
Why are we doing this project? What problem are we trying to solve? What is the current state? Try to 
summarise in five dot points. 
•  ARPANSA has accepted responsibility for the management of legacy waste generated during the 
remediation of a UoM building currently under remediation. 
•  The UoM site was once operated by the Commonwealth as the Commonwealth Radiation 
Laboratory (CRL) from the late 1920’s to the 1970’s. The activities that were conducted at the 
CRL during this time resulted in legacy contamination. Because of this the Commonwealth 
(represented by ARPANSA) is accepting responsibility for the waste produced from remediation 
of the site. 
•  Approximately 210 drums containing soil and building material contaminated with radium-226 
require storage in a licenced radioactive waste storage facility.   
•  ARPANSA’s licensed waste storage area has limited capacity for accepting more waste, however 
parts of the Yallambie site are under-used and may be adapted for low-level waste storage. A 
SWOT Analysis (available on request) has been used to identify the preferred option, that has 
been approved by the EG. 
•  The first tranche of 72 drums will be stored onsite (as soon as April 2018) as an expansion to the 
current source licence until the new storage area is completed, pending regulatory approvals. 
Scope 
The work that needs to be accomplished to deliver a product, service or result with the specified 
features and functions. 
Work to deliver a safe and secure area for appropriate storage of the legacy radioactive waste includes: 
•  Design of storage area 
•  Tender process 
•  Building works 
•  Regulatory approvals 
Transportation and storage of drums 
Timing 
How long wil  each stage of the project take to complete? 
Planning: 
Complete 
The first tranche of 72 drums will arrive at Yallambie during April 2018. 
Execution: 
The Designer was engaged late-March.  Design completion by mid-May.  Tender 
process will mean a builder is engaged in June. 
 
Closure: 
It is expected that the project wil  be closed by end of 2018 at the latest. 
Funding 
How much wil  the project cost – from costing tool, updated from project proposal phase if any new 
information is known 
Business Case v1.0 
ARPANSA-PM-TMP-002 
 
2 of 5 


Design -s 47G - business  
Relocation of Linac Chiller - $30K (aligns with Linac project) 
Building - $250K 
Transportation – 2 shipments @ $5K each. 
 
How wil  these costs be funded – does this project require additional funding from what has been 
approved in branch budgets? 
Funding for capital will come from RHS 2017/18 budget (up to $250K). 
Smal er costs, such as drums, transport and design, have not been budgeted for in 2017/18 (spent under 
RSO cost centre). 
Work health & safety 
Are there WHS implications for our people of either doing or not doing this project? Discuss with WHS 
advisor. 
WH&S adviser has been consulted during this project.   
There are no radiological dose implications from the drums (zero dose rate), and radon will be managed 
in accordance with best-practice. 
Transportation will be undertaken with a registered and experienced transport company. 
 
Security 
Are there any security implications with this project? Discuss with Agency Security Adviser 
Security implications have been discussed and advice incorporated into design of the storage area. 
Risk 
What are the risks of doing or not doing the project? 
The major risks to the Agency are; 
•  Reputational – ARPANSA must store its radioactive waste safely and securely in accordance with 
the relevant regulations and also to meet international best practice.  It would be reputationally 
damaging to the Agency to do otherwise.  There is some risk that the acceptance of this waste 
wil  be perceived badly by the immediate neighbours (see Communication activities below). 
•  Cost – This is an unbudgeted activity with potential for high costs.    
The SWOT analysis has identified these risks, and several options have been excluded due to the 
potential reputational effect.  Costs are still being determined and will be communicated regularly to the 
EG as more information becomes available. 
 
Legislation 
Are there any legislative requirements to consider? If yes, please describe. 
The ARPANSA Act and Regulations must be met as regulatory requirements will need to be satisfied. 
Business Case v1.0 
ARPANSA-PM-TMP-002 
 
3 of 5 


People 
What is the change (define the difference between current and future state)? 
The additional radioactive waste will initially be managed as a part of the Yallambie source licence 
(S0002).  The newly constructed storage area will undergo appropriate regulatory scrutiny. 
 
What is the Change Impact (define the impact the change wil  have, noting there may be multiple 
impacts for each change)? 
The radioactive waste wil  need to be managed while in storage at the Yallambie facility in accordance 
with regulatory requirements. 
Communications have been coordinated in liaison with P&C (see below). 
 
Capability – do we have the capability required to deliver on this project? If not, what is the plan for 
obtaining it? 
Yes 
 
Capacity – do we have the available capacity to deliver on this project? If not, what is the plan for 
obtaining it 
Yes 
Engagement 
Communications plan 
Consultation 
Consultations have been held with the Staff Consultative Forum (SCF), OCEO (on Communications), 
groups impacted by Linac downtime, Agency Security and ARPANSA WHS.  A lengthy discussion was held 
at the SMC on communication externally (see next paragraph).  These consultations are ongoing.   
Communication activities 
There are no community awareness opportunities relating to this item. 
Consultation with the OCEO Communications team and the SMC have determined that this activity can 
be considered to be ‘business as usual’.  As such, external communications are not recommended. 
Communications with staff have been held via ISAAC, with several staff taking the opportunity to discuss 
the project one-to-one.  No staff have expressed discomfort with the proposal at this stage.   
Staff communication is ongoing, and has been coordinated in liaison with P&C. 
 
A Talkshop will be given to update staff on the current status before the first tranche of drums is 
delivered. 
 
Behavioural change management plan 
Business Case v1.0 
ARPANSA-PM-TMP-002 
 
4 of 5 


The storage area will be safe and secure and appropriately labelled for staff.  No behavioural change will 
be required. 
Management of the waste wil  be undertaken by the RSO consistent with current source licensing. 
Consultation/collaboration 
Have we consulted with al  of the relevant people? 
See above (communication). 
 
Are there any opportunities to work with other parts of the agency? 
Col aboration has been undertaken with RHS (MERS & RPS) and the RSO. 
Interdependencies 
Pre-project completion interdependencies – are we waiting for another project to be completed 
before this project can begin? 
No.   
Consideration needs to be given to the timing of the Linac project. 
 
Post-project completion interdependencies – does another project rely on the successful completion 
of this project? 
No. 
 
Business Case v1.0 
ARPANSA-PM-TMP-002 
 
5 of 5