This is an HTML version of an attachment to the Freedom of Information request 'Hermit Park Drain Construction 1970's'.


 
TOWNSVILLE CITY COUNCIL 
PO BOX 1268, TOWNSVILLE 
Date >> 8 November 2019 
 
QUEENSLAND 4810 
 
TELEPHONE >> 13 48 10 
 
xxxxxxxxx@xxxxxxxxxx.xxx.xxx.xx 
 
www.townsville.qld.gov.au 
 
Mr David Reid 

 
xxxxxxxxxxxxxxxxxxxxxxxxx@xxxxxxxxxxx.xxx.xx 
 
 
 
 
Dear Mr Reid 
 
SUBJECT >> Request Drain Construction Information – Charters Towers 
Road, Hermit Park 
Thank you for your enquiry received 5 November 2019 regarding information on the 
Hermit Park Drain. This information relates to the concrete lined drain which extends 
upstream (east) from Charters Towers Road to Campbell Street, Hermit Park. 
 
Your questions are answered below. 
 
When was it constructed? 
The current concrete lined configuration of the drain was constructed around 1976. 
 
Purpose of its construction 
The purpose of constructing the concrete lined drain was to formalise the existing 
open drain and improve the drainage of this area of Hermit Park. This included the 
construction of a number of underground pipe systems, which drain into the 
concrete lined section. Formalising the drain also allowed land either side of the 
drain to be subdivided. 
 
What existed prior to construction of the Hermit Park Drain? 
The area was a natural drainage feature and the low point in the area, which drained 
this portion of Hermit Park. See attached figures showing the area in 1938, 1971 
before construction, 1981 after construction and now (2016). 
 
What function does the Hermit Park Drain perform? 
The function of this drain is to allow drainage of this area of Hermit Park. A number 
of underground pipe systems drain into this waterway. 
 
Why was the Hermit Park Drain constructed in its present location? 
This area was an existing open drain which was reconfigured by concrete lining and 
reshaping the drain. The location of the drain was not necessarily ‘chosen’, it is the 
low point in this area. 
PAGE >> 1 OF 2 
REFERENCE >> 2211035 DOC CSTS/19/0854 FILE CHARTERS TOWERS ROAD AXA/CS3 
ABN >> 44 741 992 072 



 
TOWNSVILLE CITY COUNCIL 
Thank you for taking the time to raise your concerns with council and I trust this 
information is of assistance. Should you wish to discuss this issue further, please 
contact council’s Stormwater Engineer Mr. Ashley Astorquia via our Customer 
Service Centre on 13 48 10. 
 
Yours sincerely 
 
Engineering Advice Team  
Infrastructure Planning, Assets and Fleet 
 
PAGE >> 2 OF 2 
REFERENCE >> 2211035 DOC CSTS/19/0854 FILE CHARTERS TOWERS ROAD AXA/CS3 
ABN >> 44 741 992 072