11 September 2020 
 
 
«Owner» 
«Mailing_Address1» 
Kardinya South 
«Mailing_Address2» 
Underground Power Project 
Property Owner Survey 
Property Address: 
McWhae
«PROP_Addr1», «PROP_Addr2» 
 
Thank you to all the residents who contributed to previous surveys regarding the proposed 
Kardinya South State Underground Power Program Project.  We are sorry for the delay in 
responding  to  you  with  the  results  of  the  second  survey  as  we  hav
- Keith 
e  been  working  with 
Western Power on the implications for the project. 
The purpose of this letter is to: 
1. 
Advise residents on the results and implications of the second survey on the Kardinya 
South Underground Power Project 
2. 
Inform residents of the revised proposal from Western Power 
3. 
Complete a third and final survey to residents 
- 20200040 
on the acceptability of holding the price 
from 2016 ($422 per property) 
The  second  survey  results  indicated  that  residents  did  not  support  the  project  at  a  higher 
average cost, with 53% (378) response rate, 39% (146) of property owners supporting the 
project and 61% (232) of property owners not supporting the project. 
Melville 
Due to the survey results the project was at risk of being cancelled.  This would result in the 
of 
overhead power lines remaining in place and significantly reduce the likelihood and viability 
of  this  area  being  considered  for  underground  power  in  the  future.    Further  to  this,  a 
significant amount of overhead network renewal works wil  need to be undertaken. 
- City 
In  recognition  of this  project  being cancelled  and  Kardinya  South  not having  the  option of 
underground  power  in  the  future,  Western  Power  reviewed  project  costing  and  examined 
other opportunities to reduce costs residents to bring them in line with the average annual 
costs per property supported in the September 2016 survey. 
In  response  to  the  State  Government’s  commitment  to  provide  funding  toward  stimulus 
Release  
projects that could be implemented in the short term to provide jobs, support the construction 
industry and boost the economy, Western Power has agreed to provide additional funding for 
the Kardinya South Underground Power Project to enable the project to be constructed at the 
FOI 
same  average  cost  as  the  original  survey  in  2016  of  $4,424  per  property  which  received 
majority support. 
As  your  property  is  in  the  area  of  Kardinya  that  has  underground  power  your  charge  is 
estimated to be $422
 
 




There  would  be  a  charge  to  your  property  as  you  are  connected  to  a  transformer  on 
Farrington Road which is in turn connected to the existing overhead network which wil  be 
undergrounded and there wil  be upgrades to the lighting in your area. 
The enclosed project facts sheet provides further detail and background information on the 
project. 
Please complete the enclosed third and final survey by returning the survey sheet and reply 
paid envelope by Friday, 2 October 2020
If the final survey results contain  more than 50% of respondents agreeing, the project  wil  
start during this financial year 2020-2021.  Properties wil  not be charged until the following 
financial year.  It wil  be included as an item in your 2021-2022 rates notice and a relaxed 
payment plan can be arranged for those with financial constraints. 
We look forward to receiving your completed survey by 2 October 2020 and wil  advise you 
of the outcome as soon as possible. 
McWhae
If you have any queries on this matter please contact the City of Melvil e on 1300 635 845 | 
9364 0666 or email melinfo@melvil e.wa.gov.au. 
Yours sincerely 
- Keith 
 
Mick McCarthy 
Director Technical Services 
 
- 20200040 
Melville 
of 
- City 
Release  
FOI 
 





Kardinya South Underground Power Project 
Property Owner Third and Final Survey 
 
 
 
Please tick the box indicating your choice; 
 
 
I Do Support  
The proposed Kardinya South Underground Power Project 
 
 
I Do Not Support  
McWhae
The proposed Kardinya South Underground Power Project 
 
 
 
- Keith 
Property Owner:  «Owner» 
Property Address:  «PROP_Addr1», «PROP_Addr2» 
- 20200040 
Melville 
of 
- City 
Release  
FOI 
 



Kardinya South Underground Power Project – Facts Sheet 
 
As your property is in the area of Kardinya that has underground power, your charge 
is estimated to be $422
What is Underground Power? 
Underground power involves removing existing overhead power lines and poles and taking 
them underground.  Some of the benefits are: 
 
Improved security and reliability of your power supply 
 
Improved and more efficient street lighting 
 
Safer environment 
 
Safer roads 
McWhae
 
Improved street view 
 
Improved property values 
 
Western Power installs the new underground cabling and  streetlights
- Keith 
 along street verges, 
connecting each home to underground power.  Once each household is connected existing 
lines and poles are removed and recycled if possible. 
 
Background of Kardinya South Underground Power Project 
First Survey (September 2016) 
- 20200040 
In  September  2016  the  State  Government,  through  the  Public  Utilities  Office,  invited  all 
affected residents in Kardinya South to take part in a survey to determine the level of support 
from property owners for underground power to be installed in the area.  
The  September  2016  survey  indicated  that  59.5%  (378)  of  respondents  supported  the 
project, which enabled the project to progress into
Melville  the detailed design phase. 
In the first survey the cost to the prope
of  rty owner was quoted to be on average a total cost of 
$4,424 per property, which at the time was the best estimate based on available information. 
Fol owing Western Power’s completion of the detailed design work, the cost of the  project 
increased by 24.5% to an average of $5,508 total cost per property. 
- City 
For  this  reason,  the  City  of  Melvil e  in  conjunction  with  the  State  Underground  Power 
Program  Steering  Committee  consisting  of representatives from, Western  Power, WALGA 
and  the  State  Government  commenced  a  second  survey  in  November  2019,  which 
concluded on 18 December 2019. 
Second Survey (December 2019) 
Release  
The  second  survey  results  indicated  that  residents  did  not  support  the  project,  with  53% 
(378) response rate, 39% (146) of property owners supporting the project and 61% (232) of 
FOI 
property owners not supporting the project. 
Due to the survey results the project was at risk of being cancelled.  This would result in the 
overhead power lines remaining in place and reduce the likelihood and viability of this area 
being considered for underground power in the future.  Further to this, a significant amount 
of overhead network renewal works wil  need to be undertaken in the near future. 
 
 



Current Situation 
 
Third and Final Survey 
 
In  response  to  the  State  Government’s  commitment  to  provide  funding  toward  stimulus 
projects that could be implemented in the short term to provide jobs, support the construction 
industry and boost the economy, Western Power has agreed to provide additional funding 
for the Kardinya South Underground Power Project to enable the project to be constructed at 
the same average cost as the original survey in 2016 of $4,424 per property which received 
majority support. 
 
Due  to  timeframes  and  the  revised  average  cost  we  wil   be  surveying  Kardinya  South 
residents for the third and final time. 
 
If the result is more than 50% of respondents supporting underground power the project wil  
McWhae
go ahead. 
 
Estimated Charges 
In establishing the estimated charges, the City has considered the following factors: 
- Keith 
 
Property density 
 
kVA requirements as advised by Western Power 
 
The City’s existing differential rating methodology for commercial properties 
 
Any existing infrastructure in-situ 
 
The charges to be levied against a property comprise of two components.  These are: 
- 20200040 
 
Contribution  to  works  external  to  the  property  which  includes  the  new  underground 
cabling,  removal  of  the  existing  overhead  powerlines,  installation  of  the  new  street 
lighting  system  and  installation  of  the  ground  mounted  transformer  and  switchgear 
cabinets.  This is identified as the Network Service Charge
Melville 
 
Contribution to the installation of a green dome and the underground cable from the 
green  dome  to  the  meter  bo
of x where required.  This is identified as the Network 
Connection Fee
The final charges to be levied for each individual property are dependant on the number of 
houses on the lot and the type of connection required at the time the project commences. 
- City 
The City is aware that there are number of properties around Arnold Crescent and Urwick 
Close that were part of a localised undergrounding of power, as part of a sub-division in the 
early to mid-1980’s.  The properties at that time were part of the City of Cockburn. 
It  is  not  uncommon  for  a  small  number  of  properties  within  a  project  area  to  have 
underground  power  as
Release     part  of  a  previously  undertaken  localised  project.    In  previous 
underground  power  projects  facilitated  by  the  City  of  Melvil e,  concessions  have  been 
applied to the affected properties in order to reflect the work previously completed and this 
wil  be do
FOI  ne in this instance. 
Western Power has confirmed that you are connected to a transformer on Farrington Road 
which is in turn connected to the existing overhead network which wil  be undergrounded. 
The cost of upgrading this portion of the network is directly related to the supply of power to 
your property.  In addition, upgrades to the existing poles and lights in your area wil  occur. 
 
 



You wil  be charged a substantially reduced network charge to cover the cost of these works 
as described below: 
Network Service Charge 
Properties included in the Kardinya South Underground Power Scheme area around Arnold 
Crescent  and  Urwick  Close  wil   each  be  charged  an  estimated  network  service  charge  of 
$422. 
Network Connection Fee 
No Network Connection Fee wil  be charged as your properties already are connected. 
 
When and How Would I be Charged? 
If  the  final  survey  results  contain  51%  or  more  of  respondents  agreeing,  the  project  wil  
commence  during  this  financial  year  2020-2021.    However  properties  wil   not  be  charged 
until the following year and included as an item in your 2021-2022 rates notice.  McWhae
 
Please  note  that  pensioners  and  seniors  who  are  eligible  for  a  State Government funded 
Pensioner  Rebate  may  receive  a  rebate  on  the  above  charges  or  defer  payment  in 
accordance with the provisions of the State Government’s Rates and Charges (Rebates and 
- Keith 
Deferments)  Act  1992.    The  City  wil   also  work  closely  with  residents  to  help  develop 
payment plans that match individual financial circumstances. 
 
Payment can be made in instalments over an extended period of time, incurring a minimal 
interest  charge  (currently  2%)  which  is  determined  each  year  by  Council.    If  you  are 
interested  in  an  extended  payment  plan  please  contact  the  City’s  Rates  Department  on  
1300  635  845  |  9364  0666  or  melinfo@melvil e.wa.gov.au  when  you  receive  your  
2021-2022 rates notice. 