This is an HTML version of an attachment to the Freedom of Information request 'FOI Request - PEMS'.

Released by the Department of Finance under the Freedom of Information Act 1982
FOI 22/104 - Document 01
Steering Committee meeting – 28 April 2022 
Parliamentary Expenses Management System 
Recommended actions 
It is recommended that you: 
1. Accept the Minutes of the previous meeting and the status of actions.
2. Accept the project update and integrated project schedule:
a. Refer Project Status Report as at 22 April.
b. At 22 April, Phase 2 was 71% complete against planned completion of 73%. The
schedule performance index (SPI) is 0.97.
The PEMS Functional Testing finished on 15 April as per the schedule:
• 96% of testing overal  was completed.
o
98% of tests passed for functional modules.
o
89% of IPEA reporting test cases were completed and passed.
 Expenditure Reporting 86% complete.
 Budget Reporting 77% complete.
 Report Security 100% complete.
 Ad-Hoc Reporting 100% complete.
• The focus is on defect remediation and retesting and the related
retesting of failed or blocked test cases.  There are 65 items
remaining to remediate in the period to 6 May 2022.
IPEA wil  continue to test for Expenditure Reporting with 37 tests to
be completed by 6 May 2022.
3. Note the PEMS Communication Plan approved by Project Board on 27 April 2022.
4. Note the Readiness Scorecard at 22 April 2022. The first Readiness checkpoint
(Checkpoint 1) meeting was held on 21 April, with the fol owing recommendations
made:
• Continue to progress readiness activities;
• Increase from one to two stand-up meetings per week for tracking Readiness
Activities (to be increased to daily meetings from June through to go-live);
• Readiness Team chair to advise the Decision Team of the Recommendation Team
meeting outcomes (completed).
5. Note the financial position as at 31 March 2022.
6. Note the Gateway Mid-Stage Review report and Accept its Recommendations.
1 of 18


FOI 22/104 - Document 01
2 of 18

FOI 22/104 - Document 01
Action Items 
Item 
Action 
Owner 
Status 
Comments 
Actions from meeting of 21/12/2021 
A102 
Testing progress report to be provided regularly to 
PO 
In progress 
27/04/22 – testing status as at 15 April to be presented at the 
the Steering Committee. 
meeting. 
7/04/22 – refer attached Testing Dashboard as at 8 Apr. 
7/03/22 – refer attached Testing Dashboard as at 4 Mar. 
7/02/22 – refer attached Testing Dashboard as at 7 Feb. 
21/01/22 – refer attached Testing Dashboard as at 21 Jan. 
Actions from meeting of 10/02/2022 
A104 
If appropriate, circulate the governance paper 
PO 
In progress 
27/04/22 – as per previous update on 7/03/2022 Also refer to 
previously circulated to members to review 
Gateway Review team’s recommendation. 
anticipated activities post Go-Live, as well as provide 
7/03/22 – governance paper undergoing update following 
an understanding of what is in the backlog and the 
feedback from MaPS. An understanding of the backlog and 
resources required to deliver. 
assessment of resources required to deliver will be covered under 
the work to estimate the support cost for 2022-23. 
Actions from meeting of 10/03/2022 
A105 
Provide progress updates to the Steering Committee 
PO 
In progress 
22/04/22 – Daily reporting to Project Executive; Project Executive 
about report testing, including any additional 
provides regular briefing to SC Chair; weekly meetings between 
assistance from Project, SDO and IPEA. 
IPEA Executive, SC Chair and Project Executive. 
7/04/22 – refer attached Testing Dashboard as at 8 Apr. 
A106 
IPEA to advise the Steering Committee of its 
IPEA 
In progress 
7/04/22 – IPEA to provide an update at the meeting. 
Members’ support of continued quarterly reporting in 
the immediate period post Go-Live. 
 
3 of 18


FOI 22/104 - Document 01
Parliamentary Expenses Management System 
(PEMS) Project 
Steering Committee – Draft Meeting Minutes 

Meeting Details 
Date: 
Thursday, 28 April 2022  
Time: 
9.30am to 10.30am 
Venue: 
GovTEAMS video conference 
Attendees:  Ms. Clare Walsh – Chair 
Mr. John Sheridan – Project Executive 
Mr. Michael Frost representing Annwyn Godwin – Senior User, Independent 
Parliamentary Expenses Authority (IPEA) 
Mr. Dean Edwards representing David De Silva – Senior User, Ministerial 
and Parliamentary Services (MaPS) 
Ms. Michelle Black – Senior Supplier, Service Delivery Office (SDO) 
s 22
 representing Simon Quarrell – Member, Digital 
Transformation Agency (DTA) 
Mr. Peter Rush – Member, Prime Minister and Cabinet (PM&C) 
 
Advisers 
s 22
 – A/g PEMS Branch Director and Senior Supplier, ICTD 
s 22
 – PEMS Project Manager, ICTD 
s 22
 – A/g PEMS Director, ICTD 
 
Secretariat 
s 22
 
1.  Meeting Opening 
Summary 
Apologies 
Annwyn Godwin – Senior User, IPEA 
Mr. Simon Quarrell – Member, DTA 
 
Minutes 
The Minutes of the meeting of 10 March 2022 were accepted.  
 
Actions 
A102 – Testing progress report to be provided regularly to the Steering 
Committee: 
•  This phase of the Project has now passed, with only 8 tests not 
completed by the deadline of COB of 14 April 2022 (last working day 
before 15 April 2022). 
4 of 18

FOI 22/104 - Document 01
•  Most of the remaining test cases are in relation to expenditure reporting. 
The remaining tests will be progressed 15 April and 06 May 2022 in 
parallel with the testing defect remediation period. 
•  Close. 
 
A104 – If appropriate, circulate the Governance paper previously circulated 
to members to review anticipated activities post Go-Live, as well as provide 
an understanding of the backlog and the resources required to deliver: 
•  The Project wil  review the Governance paper and consider 
Recommendation 6 to: 
o  Review the proposed governance model for the post Go-Live and 
BAU phase of the Project to provide greater clarity about how the 
governance model will operate in practice and reflect SDO 
processes and requirements. 

•  The paper requested by the Chair wil  report the Project’s consideration 
of this Recommendation and will be delivered at the agreed time. 
•  Close. 
 
A105 – Provide progress updates to the Steering Commit ee about report 
testing, including any additional assistance from Project, SDO and IPEA: 
•  Daily meetings and subsequent reporting to the Steering Commit ee 
Chair has occurred during the testing period, which has been surpassed. 
•  Close. 
 
A106 – IPEA to advise the Steering Committee of its Members’ support of 
continued quarterly reporting in the immediate period post Go-Live: 
•  The IPEA Senior User advised that IPEA Members are supportive of 
transitioning to monthly reporting only when the PEMS reporting solution 
is fully implemented and functioning as planned. 
•  IPEA Members are also supportive of the IPEA Executive making this 
decision. 
•  Close. 
 
Closed Actions 
A102, A104, A105 & A106. 
Decisions 
The Steering Committee accepted the minutes from the previous meeting 
as well as the status of actions raised. 
Actions 
Nil 
2.   PEMS Delivery Update 
Summary 
Phase 2 Status Report 
The Chair presented the schedule as at 22 April 2022: 
•  PEMS is currently reporting Green as a consequence of moving to the 
post-testing phase. 
•  The Project is 71% complete against a plan of 73%, with the Schedule 
Performance Index (SPI) recorded as 0.97. 
•  Defect remediation is underway with 17 items transported to the UAT 
environment and 5 test cases passed since 15 April 2022. 
5 of 18

FOI 22/104 - Document 01
•  The Project team is confident the remaining work can be managed. 
Remediation of the items is required to be resolved by 06 May 2022. 
•  ICTD provided a review of the Accessibility Testing report that is largely 
compliant with no critical issues to address for the 1 July 2022 Go-Live. 
•  SAC Penetration Testing has concluded and a draft report provided to 
the Project for review. Response to testing provider to confirm scenarios 
covered prior to accepting the Report. 
•  The transactional (ECC system) SAP code review saw no critical issues. 
•  An assessment of the Business Warehouse (BW) code is complete with 
similar findings to ECC review (no critical issues). 
•  An action plan wil  be implemented as part of continuous improvement 
which wil  include remediation steps for the small number of low-risk 
items identified in the reports conducted thus far. 
•  The external agency members congratulated the Project Executive and 
the broader team on the tremendous work to improve the current 
delivery status.  
•  The Chair also expressed their appreciation on the massive efforts to 
IPEA and the Project team to complete the large scale of testing cases. 
 
Risks and Issues 
The Project Executive discussed the following PEMS Risks and Issues: 
•  (New) Issue #35 – Travel provider change with CTM wil  not be 
implemented by Go-Live as the PEMS defect remediation period closes 
on 06 May: 
o  The front-end changes are mainly labelling and have been 
completed. However the file format that the provider provides to 
IPEA wil  change in the back-end from 01 July 2022. 
o  This approach was discussed at the Project Board, with IPEA to 
engage with the provider and communicate the urgency of what 
is required as well as continue investigating the most suitable 
solution (either a technical or CTM adjustment to the file format). 
•  (New) Risk #68 – Product verification testing (PVT) cannot be 
undertaken by the external users at Go-Live: 
o  MaPS to confirm URG test users for the weekend of Go-Live to 
verify the system is functioning – this list wil  be available after the 
Federal election proceedings. 
o  MaPS wil  also advise on a cohort who may not be affected by 
the election. 
o  MaPS and IPEA will also undertake their respective PVT as 
required. 
o  The Project can accept the risk given functionality has been well 
tested in the lower environments; MaPS and IPEA staff to 
validate tiles in the same way as previous production CDR/code 
release weekends and Project team to determine how PVT can 
be managed for external client applications and functions. 
 
Testing and Defect Remediation 
•  Of the 65 items that remain to be completed, 31 items are currently in 
development for remediation, of which: 
o  16 are Defects 
6 of 18

FOI 22/104 - Document 01
o  3 are Gap Defects, and 
o  12 are Change Variations. 
•  34 items are currently being tested by the Business and the Test Team – 
the breakdown is as follows: 
o  8 x Common Items 
o  5 x Budgets 
o  3 x Domestic Travel 
o  2 x Office Expenses 
o  4 x International Travel 
o  11 x Reporting (of which 8 relate to Expenditure Reporting), and 
o  1 x EMS - Entitlements Management System. 
•  There are 95 self-service reports listed to be delivered. The Project is 
confirming their priority for Go-Live and the status of their build with 
IPEA. Work to date to produce the priority reports is progressing well. 
•  The Project Board agreed to two remaining Changes be included: 
o  Change Request #5602: Domestic Travel – the comments should 
be optional and not mandatory, and 
o  Change Request #5858: Reporting (Budget Reports) – adding a 
footer to the budget summary page and each of the budget 
consumption reports. 
•  A third Change Request to resolve an issue with International Travel 
relating to users that incur international travel expenses but do not incur 
travel allowance is being assessed to decide if it can be deferred until 
the first release post Go-Live or fixed by 6 May. 
o  The risk of undertaking this work by 06 May 2022 is that it may 
not be completed given other priorities. 
 
Production Phase 1 Support Update 
•  As at 22 April 2022, PEMS remains a healthy system with no significant 
underlying themes. 
•  Of the 5 open tickets, two have been open for more than 28 days: 
o  #1650501 – SAP Creation of customer records for active MoPS 
Act HR records. This ticket is waiting for IPEA to provide 
populated file to the SDO to upload bulk customer in lower 
environments, and 
o  #1653219 – Create an ESA adjustment code in SAP. It can 
progress to Production on the next available CAB release when 
UAT has been completed by Business. 
•  The planned Alemba (vFire) upgrade has been postponed until the loss 
of key ‘drag and drop’ feature for attachments is resolved. 
•  The Project Executive has given guidance to the Assistant Secretary 
responsible for managing this tool to engage with the service provider to 
express Finance’s dissatisfaction and seek the appropriate resolution. 
•  User registrations remain consistent at 85%, despite a recent Senator 
change that has resulted in an additional unregistered member. 
Decisions 
The Steering Committee accepted the Project update and integrated Project 
schedule. 
Actions 
A107 – MaPS to advise a cohort of URG members to be involved in PVT. 
7 of 18

FOI 22/104 - Document 01
3.  PEMS Communications Plan 
Summary 
•  The PEMS Communications Plan (the Plan) was approved by the 
Project Board on 27 April 2022. 
•  The Chair confirmed that the Steering Committee also approve the Plan 
by COB 03 May 2022. 
•  In summary the Plan: 
o  is routine and includes the initial external message published on 
the MaPS’ website which will direct users to the PEMS landing 
page for further go live updates 
o  discusses targeted user cutover information, such as completing 
their claims by the relevant date to avoid unnecessary 
complaints, as the functionality wil  not be transferred and will 
lapse 
o  MaPS and IPEA wil  be provided with the function of viewing in-
flight transactions to verify if users have incomplete transactions 
in the system. 
•  The Chair also requested information about PEMS is included in the new 
starter induction process. 
Decisions 
The Steering Committee did not note the PEMS Communications Plan 
already approved by the Project Board. 
Actions 
A108 – Distribute the PEMS Communications Plan out-of-session for the 
Steering Committee’s response by COB 03 May 2022. 
4.  Readiness Scorecard 
Summary 
•  The first Delivery Checkpoint meeting was held with the 
Recommendation Team on 21 April 2022 with the following 
recommendations agreed: 
o  Continue to progress readiness activities, 
o  Increase from one to two stand-up meetings per week for 
tracking Readiness Activities (to be increased to daily meetings 
from June 2022 through to Go-Live), and 
o  The Decision Team be advised of the Recommendation Team’s 
meeting outcomes as well as receiving the updated Scorecard to 
review the high level of detail. 
•  The second Checkpoint Meeting is scheduled for 04 May 2022. 
Decisions 
The Steering Committee noted the Readiness Scorecard as at 22 April 
2022. 
Actions 
Nil 
5.  Financial Position 
Summary 
•  The Steering Committee reviewed the financial position as at 31 March 
2022, noting no major changes have occurred and the Project is stil  
tracking against budget. 
•  The actuals were previously recorded to including the recovery (revenue) 
from IPEA, the way this was recorded has been changed to show the 
actuals exclusive of the revenue from IPEA.  
•  The funding has been updated to include the funding from IPEA and  
upon realising the $600k funding assistance from IPEA. 
•  This minor complication of addressing the additional funding as an 
increase to the Project’s budget wil  be discussed in detail with CFOB 
8 of 18

FOI 22/104 - Document 01
and IPEA to ensure it is explained correctly should this be raised in 
Estimates. 
Decisions 
The Steering Committee accepted the 31 March 2022 financial position.  
Actions 
Nil 
6.  Other Business 
Summary 
Gateway Review Report 
•  The Project’s proposed response is to accept all Recommendations and 
track the associated actions, in addition to the paper requested by the 
Chair on a number of matters including post Go-Live governance. 
•  The Project Executive suggested maintaining existing Project 
governance mechanisms until December 2022, to allow for continual 
management post Go-Live, such as the ongoing expenditure report work 
to be delivered by October 2022 as well as the backlog items. 
•  Extension of the governance mechanism wil  not be at any additional 
cost as the APS resources are funded by the ICT Division.  
•  The estimated $4m funding allocated for sustainment of BAU (once 
achieved) wil  also assist with several other gateway Recommendations. 
•  The benefits realisation (Recommendation 8) wil  be better understood in 
December 2022, with the Project stil  in effect. 
•  The anticipated paper requested by the Chair wil  include more detail of 
these suggestions for consideration by the Steering Committee, following 
consideration by the Project Board. 
•  Close consultation with IPEA and MaPS will occur in preparing the paper 
noting decisions scheduling backlog implementation is the responsibility 
of the business areas. 
•  The Chair requested a continuation of the actions taken by the Project as 
wel  as changes to the Steering Committee’s roles and responsibilities 
be reported clearly in the paper, as well as monthly action updates. 
 
Final comments 
•  The Chair once again expressed her gratitude to the Project Executive 
and all stakeholders and Project team members involved in succeeding 
in the remarkable volume of work delivered thus far in the Project. 
Decisions 
The Steering Committee accepted the Gateway Mid-Stage Review Report 
and agreed its recommendations and the Project’s proposed actions. 
Actions 
Nil 
The meeting closed at 10:15am.  
9 of 18


FOI 22/104 - Document 01
10 of 18


FOI 22/104 - Document 01
11 of 18






FOI 22/104 - Document 01
Refer Attachment 2 - Project Risks  
 
 
•  Risks are reviewed and updated regularly. 
Risks 
•  The next Risk Workshop is scheduled for Wednesday 1 June 2022.  
 
  •  68 risks have been raised; of the 17 open risks, 1 is high, 6 are medium and 10 are 
low. Two Low rated risks have been transferred to a BAU Risk Register. 
Penetration Testing of SAC 
Quality 
•  SAC penetration testing concluded with three (2) low risk and (1) informational 
 
 
issues identified. The findings will be captured in the security action plan. 
 
•  Draft design documentation has been provided to the SDO. With the build and 
Design 
 
 
testing finalised, updating/creation of system documentation can now progress. 
 
•  Build and remediation of Phase 2 essential items and prioritised backlog is 
Build 
 
 
complete. 
Key activities and progress as at 6 May: 
•  The agreed functional / user acceptance testing cycle, and the extended defect 
remediation periods have ended.  
•  The project team will prepare a UAT Exit Report for the Project Board 
 
Testing 
consideration. 
 
  Remaining Test Cases  
•  No test cases remain for execution in Phase 2. 
Remaining Work Items: 
•  All agreed items have been completed. 
Phase 1 
•  A weekly dashboard is distributed to Senior Users. There are no issues of concern.  
Phase 2 
Support 
 
 
•  Comments have been received on the draft transition plan and is now being 
Organisation 
 
 
finalised. 
•  Knowledge transfer sessions to the SDO support team have commenced. 
•  Draft Service Catalogue has been provided to SDO and will be updated during 
support discussions over the next few weeks. 
•  External communications to Parliamentarians and MoP(S) staff has commenced. 
Change 
•  System Instructions and How to Guides have been drafted and are under review by 
Management 
 
 
Business. 
and 
 
  •  MaPS internal training commenced on 2 May. 
Communications 
•  IPEA is preparing a separate training plan, feedback has been provided by the 
project and the plan is expected to be finalised by the end of May. 
•  The project team and MaPS are progressing updates to the Operational Governance 
 
 
arrangements for post Phase 2 go-live. 
Readiness 
•  Readiness activity tracking meetings are held bi-weekly, the second Checkpoint 
 
 
meeting was held on 4 May 2022 and agreed to proceed with readiness 
•  At 6 May, of the 131 Total Activities, 92 are on track and 39 are completed. 
 
Legend: On Target 
Alert 
Escalate 
Overall 
 
 
 
Green Light Criterion = 
All green, or only one amber with no red 
 
 
 
Amber Light Criterion = 
Identified issues being managed and  Issues are likely to affect the 
Issues will have a significant effect  More than one amber but no red 
updated regularly  
implementation effort if action is 
on the implementation effort if 
Red Light Criterion =  
not taken and managed  
action is not taken and managed   One or more red 
12 of 18


FOI 22/104 - Document 01
13 of 18


FOI 22/104 - Document 01
14 of 18


FOI 22/104 - Document 01
ATTACHMENT 3. HIGH LEVEL SCHEDULE FOR PHASE 2 
 
 
15 of 18

FOI 22/104 - Document 01
PEMS financial position summary as at 30 April 2022
Summary of the total funds al ocated and funds estimated to complete 
the project in 2021-22.
2017-18 
2018-19 
2019-20  2020-21  2021-22  Totals 
Approved  2020-21  2021-22  Totals 
($m)
($m)
($m)
($m)
($m)
($m)
to date 
($m)
($m)
($m)
($m)
Funding
2.7
19.4
21.9
8.7
6.7
59.4
2017-18 MYEFO
34.1
34.1
Actual
2.7
19.4
21.9
8.7
5.6
58.3
MYEFO 2017-18 Ongoing
4.0
4.0
8.0
Development
Committed
0.0
0.0
0.0
0.0
0.3
0.3
IPEA
5.0
0.0
0.6
5.6
Uncommitted 
0.0
0.0
0.0
0.0
0.8
0.8
Finance 
4.9
7.8
5.4
18.1
Surplus(+)/ Deficit(-)
0.0
0.0
0.0
0.0
0.0
0.0
Total 
44.0
11.8
10.0
65.8
Funding
0.0
0.0
0.0
2.9
3.5
6.4
SDO SaaS
2.9
3.5
6.4
SDO Support &  Actual
0.0
0.0
0.0
2.9
2.9
5.8
Total excluding SaaS
44.0
8.9
6.5
59.4
Maintenance  Committed
0.0
0.0
0.0
0.0
0.6
0.6
(SaaS)
Uncommitted 
0.0
0.0
0.0
0.0
0.0
0.0
Surplus(+)/ Deficit(-)
0.0
0.0
0.0
0.0
0.0
0.0
Funding
2.7
19.4
21.9
11.6
10.2
65.8
Actual
2.7
19.4
21.9
11.6
8.5
64.1
Total
Committed
0.0
0.0
0.0
0.0
0.9
0.9
Uncommitted 
0.0
0.0
0.0
0.0
0.8
0.8
Surplus(+)/ Deficit(-)
0.0
0.0
0.0
0.0
0.0
0.0
16 of 18


FOI 22/104 - Document 01
17 of 18


FOI 22/104 - Document 01
18 of 18